Saudi Arabia (AS.SA)

SA

Ashraf Kadri

First Name
Ashraf
Last Name
Kadri
Professional Since
Years Experience
0
LinkedIn Profile
https://www.linkedin.com/profile/view?id=AAIAAAWNl5IBy94fy2ox1cZg71dk6-hsq3cN3Qo&trk=nav_responsive_tab_profile

1-Organization:Jacobs Zate, Al-Khobar, Saudi Arabia (July 2015 to date)

Client: SAUDI ARAMCO - General Engineering Services Contract

Designation: Project Engineer 

 

Projects:

A - BI-10-00778Replacement of 3 Substations at Riyadh Refinery

B - BI-10-01522  Replace Pressure Vessels – South Ghawar

 

Lead Planner / Project Controls Manager, Arcelor Mittal, Arcelor Mittal Tubular Division

S
Sajan Kumar 👤 Member for 22 years 9 months
START Date
END Date

Responsible for preparing and updating resource loaded schedules. Scheduling performed utilizing Primavera P6.2 to produce CPM Schedules and associated progress reporting, cost reporting and project analysis. Scheduled all activities associated with the project to produce an integrated critical path schedule, updated weekly and reported potential problems to the Project Manager. While updating the schedule, evaluated the accuracy of the project forecast by assessing actual cost incurred and physical progress achieved for all phases of the project.

Ronald Rafer

First Name
Ronald
Last Name
Rafer
Professional Since
Years Experience
0
Facebook Profile
http://www.facebook.com/mastercoolass
Twitter Profile
@ronraf2010

·         With self confidence and initiative, can accomplish any assigned task to the complete detail.

·         Independent handling of complex task and responsibilities.

·         Fully conversant with computer applications under windows environment.

·         Open for learning new things.

Senior Lead Planning Engineer, SAHARA PETROCHEMICAL, Triennial Turnaround of the Polypropylene & Ethylene Production Plant

M
Mufiz Sayed 👤 Member for 17 years 8 months
START Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
2000
  • Responsible for monitoring, controlling and directing the Maintenance Planning group.
  • Develops strategic turnaround plans and maintains the 5 year projected turnaround schedule. 
  • Ensures that T/A industry best practices are utilized
  • Drives alignment on T/A objective with the core team
  • Stewards the risk-based turnaround work scope development and management process.&nbsp

Planning Engineer, AZMEEL CONSTRUCTION COMPANY, Royal Commission - Construction Of Apartment Buildings

START Date
Experience Hours (Planning & Scheduling)
5000

Job Responsibilities

·         Preparing master schedule & the baseline schedule.

·         Selects the most appropriate techniques and logical sequence of activities to complete project scope.

·         Set up issue alerts for all important contractual and milestone dates.

Planning Engineer, AZMEEL CONSTRUCTION COMPANY, Royal Commission - Construction Of Apartment Buildings

START Date
Experience Hours (Planning & Scheduling)
5000

Job Responsibilities

·         Preparing master schedule & the baseline schedule.

·         Selects the most appropriate techniques and logical sequence of activities to complete project scope.

·         Set up issue alerts for all important contractual and milestone dates.