Project Planner, BLACK & VEATCH International, 1.Refurbishments[Design, Supply, Installation, Construction, commissioning and testing] Lane End WTW [3 million Pound starlings],2.Refurbishments[Design, Supply, Installation, Construction, commissioning and

START Date
END Date

Responsibilities discharged   

  • Develop the Schedule, Set up the base line
  • Resource loading, Target setup
  • Coordinate with project team
  • Attain the meeting and follow the guideline and Collect the data from project
  • Monitoring the Sub contractor works and update the Schedule accordingly
  • Update the schedule and analysis the Current float and critical path.
  • Advice the project manager for critical activities and concern cause.
  • Produce Monthly Project Fina

Project Planner, ABB Ltd, 1.Replacement of Wakefield B 132 kV GIS – 15 Million GBP [ Client CE Electric ], 2.Walpole 132 kV GIS, SGT5 and Centrica Bas Bar Extension – 35 Million GBP [ Client National Grid]

START Date

 

Project Planner/Mechanical Engineer

(17 years experience)

 

  • Prepared, maintained and monitored project plans/schedules.
  • Significant skill on Planning Tools [ Primavera P3 version 3.1,Microsoft Project]
  • I got training on Planning Tools P6 and currently working on P6.
  • Performed critical path analyses, earned value analyses, resource leveling.
  • Involved with site planning in terms of programming and progress monitoring.
  • Worked / lia