I have worked in the Oil ad Gas industry, both in Perth, Western Australia and in Aberdeen, Scotland. I started out as an Assistant, learning the basics from the ground up. Since my first position, i have since progressed and used Primavera P6 and P3E, as well as Microsoft Project. Other programs such as Excel and Access are others i am proficient in.

Planner, Enermech, Schiehallion Mooring Line Replacement

START Date
END Date

 

  • Developed a detailed Level 3 Installation schedule, in line with the projects WBS structure, using Microsoft Project.
  • Liaised with the Project Engineer on different installation options and produced a series of option plans for issue to the client.
  • Attended weekly client meetings, and advised on various installation options.

Tracked and issued progress to the client on Workpack status

Planner, Technip, Devenick

START Date
END Date

 

  • Work closely with the Project Team to create Level 3 Tender schedules for various projects and clients, in MS Project 2007.
  • Create various option schedules to cover all client options, and compare schedule impact between the options with the project team.
  • Once awarded, convert the project into P3 and include costs, and track progress.
  • Issue monthly S-curves and histograms to the project team, for inclusion into the monthly report to the client.

Assistant Project Manager / Project Planner, NEXEN, Blackbird

START Date

Setup, Planned and Executed Project Master Schedule from Sanction to First Oil.

Brought all facets of the project together using an integrated WBS structure.

Tracked All Subcontractors through the schedule to ensure timely delivery.

For the final Implementation phase, created a detailed Implementation schedule to bring all the interfaces of the project together, managing multiple simops and workfronts.