Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Planning Engineer, Bombardier, SSL

START Date
END Date

Schedule emerging work during the realisation phase of the project

Estimate anticipated work during this phase

Provide a forecast each month of the remaining work

Monitor progress through one to one meetings with lead engineers and daily visulisation meetings

Provide data for KPIs

Project Coordinator, Yokogawa Engineering, (various projects)

START Date

Responsible for project document control, logging and maintaining electronic and hard copy documents to provide easy access to project staff and engineers

• Liaised with Project Managers and updated SAP with changes, providing checks to ensure cost allocations were correct and project remained profitable

• Prepared project plan with Project Manager based on client requirements

• Compiled quotations for customers in terms of service contracts, liaising with Procurement Department to incorporate supplier costs into the quotation

Project Coordinator, Yokogawa Engineering, (various projects)

START Date

Responsible for project document control, logging and maintaining electronic and hard copy documents to provide easy access to project staff and engineers

• Liaised with Project Managers and updated SAP with changes, providing checks to ensure cost allocations were correct and project remained profitable

• Prepared project plan with Project Manager based on client requirements

• Compiled quotations for customers in terms of service contracts, liaising with Procurement Department to incorporate supplier costs into the quotation

Improvement Planner, London Underground, Various

START Date
  • Liaising and challenging the project leads and asset areas to ensure individual projects deliver programme targets (project management and cost plans) which are easily evidenced.
  • Higher level planning and reporting requirements of the programme in order to maintain service excellence, the dynamic APD Efficiencies model, achieve the company’s objectives and influence overall Programme & Project performance towards them.
  • Helping identify, generate and drive a climate and process of opportunities for Continuous Improvement to cost effectively improve planning and

Workstream Planner, London Underground, London Underground Various

START Date
END Date

My responsibilities in this role include developing and applying a standardised and consistent approach to long term strategic planning across the Asset Performance directorate and ensuring adherence to programme governance and change control regulations.  These activities are carried out whilst ensuring they support and are aligned to the larger-scale business plan and Annual Asset Management Programme.  Consideration is given to a wide variety of factors with particular focus on risk management, engineering issues, finance, SQE and potential HR/ER iss

Jason Mills

J
Jason Mills 👤 Member for 15 years 5 months
First Name
Jason
Last Name
Mills
Professional Since
Oldest experience
Years Experience
42
Telephone Number
07414545689

A project Control Engineer since 2006, currently working on a Substation replacement project. The role encompasses planning, cost management and contract management. I can compertently use Primavera P6, PRISM, SAP and all the microsoft applications. I have the NVQ 3 in Project Controls, Earned Value foundation and Earned value practitioner throught the Association of Projeect Management (APM and am currently studying for a Fdsc in Project Management and Control.