PLANNING ENGINEER, Whessoe LGA Gas Technology, Dabhol LNG Project, Depa LNG Tankage Project, Kotri Barrage Rehabilitation Project, Hammerfest LNG Project

START Date
END Date
Experience Hours (Planning & Scheduling)
6500
Experience Hours (Cost Management)
500

During my time at Whessoe, I was employed at the head office on both live contracts and tenders, using Primavera P3, Suretrak & Microsoft Project 98 computer systems, with supporting documentation produced using various Microsoft packages. In this time I have worked on design only projects, EPC projects, tenders and FEED studies.

PLANNING ENGINEER, AMEC Capital Projects (Downstream Oil & Gas), BP CATS Valve Upgrade Project, Bathgate Gas Compressor Station New Works, Kings Lynn Gas Compressor Station Upgrade Project

START Date
END Date
Experience Hours (Planning & Scheduling)
6350
Experience Hours (Cost Management)
500

During my time at AMEC I worked at both the Darlington office and various sites, on live contracts, tenders and FEED studies, using both Primavera P3 and Suretrak computer systems, with supporting documentation produced using various Microsoft packages in-line with the company’s CTR system. In this time I have worked on design, construction, EPC projects and shutdowns.

PLANNING ENGINEER, Whessoe Oil & Gas, Adriatic LNG Terminal, EBIC Ammonia Plant Project, Panipat Ethylene & Propylene Plant Project

START Date
END Date
Experience Hours (Planning & Scheduling)
4700

Working at the head office in Darlington on both live contracts, tenders and FEED studies, using both Primavera P3 and P5 (P3e) computer systems, with supporting documentation produced using various Microsoft packages in-line with the company’s CTR system. In this time I have worked on design, construction and EPC projects. Responsible for programme setup / development, progress monitoring and reporting.

Karl Wilkinson

First Name
Karl
Last Name
Wilkinson
Professional Since
Oldest experience
Years Experience
14
Telephone Number
07815 723 494

Primavera P3 to P7, Microsoft Project, EUSR, PTS (UK & NI) AC/DC and Medical, PPS IPCS PMCS, CCMS, TILOS.

Planning and Scheduling, Dashboard Reporting, EVA, Claims, Delay Analysis, CP Analysis, 14 Point Schedule Assessment, Tender Planning, Consortium Planning, Tender Assessments, Time Chainage, Cost Control and Forecasting.

AACEI - Member

APM - Associate Member

Core senior Planner, Networkrail, IPEM

START Date

Network Rail / EC Harris(IPEM – Derby)

-          Lead planner for Building and Civils Team. Platform Extensions, AfA Schemes, as part of Kidsgrove, Alfreton, Fiskerton and Lowdham, LDHSS, Nottingham Porte Cochere commissions.

-          Responsible for building best practice programmes from first principles covering all GRIP stages.

Benjamin Stanley

First Name
Benjamin
Last Name
Stanley
Professional Since
Years Experience
0

My current role is that of a project controls engineer on a Nuclear project, this has required me to develop and maintain a  level 4 schedule in accordance with NEC3 requirements, my other responsibilities include, but are not limited to: maintaining progress measurement against the engineering deliverable, providing the client with a man-hour forecasts, baseline management, change control and mitigation planning. Previously I was responsible for maintaining and developing the Engineering Schedule which is part of an overall EPCM Project currently being executed in Greece.

Freelance Senior Planner, Volker Laser, A58(M) Woodhouse Tunnell Strengthening, Leeds

P
Paul Ross 👤 Member for 23 years
START Date

January 2014 – date - Ross Planning contract for VolkerLaser – A58(M) Woodhouse Tunnel Strengthening, Leeds, analysis in MS Project & P6

Conversion of Carillion P6 programmes into MS Project, initial analysis of 4 or 5 (very large ~ 4600 activities) programmes plus a watching brief for VolkerLaser interests as the programmes are issued and updated. Most work done from home with occasional site meetings.

Lead Asset Planning Engineer, CNR International, CNRI North Sea Offshore Assets

START Date
END Date
Experience Hours (Planning & Scheduling)
700
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
0

Integrated Asset Plans for all CNRI UK offshore platforms, Shutdown & Project Plans, Business / Strategic Plans, KPI Reports, S Curves, Histograms, Progress reports.Review, Validate & Intergrate Contractor schedules into the Integrated Plan. POB Forecast at Strategic /Tactical, 6Q, 90 Day and 28 Day levels. Planning & Progress Meetings with stakeholders, What-if Scenarios. Liase with Senior Project and Discipline Engineers and different departments. Risk analysis workshops for major projects. Manage the interface between the Planning Tools (P6, MSP  & Maximo).