Junior Planner and Controller, Infrastrutture Lombarde S.p.A., Expo 2015
Main works
- Tender contract for the execution of works called Piastra, related to the site of EXPO 2015
- Tender contract for the planning and the execution of works called Architetture di Servizio, related to the site of EXPO 2015
- Tender contract for foundation works for future buldings planned on the site of EXPO 2015
Skill acquired:
- Work planning and accounting
- State of Progress checking, critical variance analysis of the forecast and data acquisition for internal reporting
- Administ
Junior Planner and Controller, Infrastrutture Lombarde S.p.A., Expo 2015
Main works
- Tender contract for the execution of works called Piastra, related to the site of EXPO 2015
- Tender contract for the planning and the execution of works called Architetture di Servizio, related to the site of EXPO 2015
- Tender contract for foundation works for future buldings planned on the site of EXPO 2015
Skill acquired:
- Work planning and accounting
- State of Progress checking, critical variance analysis of the forecast and data acquisition for internal reporting
- Administ
Matteo Agliocchi
Eldar Mardanov
I have 13 years working experience in project controls & management of the onshore and offshore oil & gas industry and mining, working for many major Oil & Gas company’s as a contractor such as B.P, Exxon-Mobil, Shell, Eni, Saudi Aramco, DNO, Cameco. Involving the design, planning, cost estimation,budgeting, construction and commissioning phases of several major national and international offshore projects and onshore process facilities.
Morena Manai
Building construction engineer, proficient in Project Management. Thanks to university studies I got the knowledge of methods and tools necessary for the design of building construction, town planning and energy saving. The work experience has allowed me to explore not only the design process but also the execution and the management of the work created.
Marta Pillinini
Giordano Picco
Project planner, Cimolai, Maintenance Hangar Doha Airport, Warsaw National Stadium
I worked as a planner in several international project in the last 8 years for a big structural steel fabrication and erection Italian company.
I've been working trought several project in Qatar, Poland, Italy, Panama working with Primavera P.3 and P.6 for scheduling and reports.
Site Planner, Cestaro Rossi S.p.A., Sulphur Plant Unit U 2900 (Eni Refinery) - Taranto (Italy)
development baseline schedule, maintenance schedule, weekly/monthly reports, identification variances to planned performance,