Senior Project and Construction Planner

Senior Project and Construction Planner, Flsmidth, Out of Pit Crushing & Conveyor System Project

START Date
END Date
Experience Hours (Planning & Scheduling)
450
Experience Hours (Cost Management)
350
Experience Hours (Forensic Analysis)
200

Out of Pit Crushing and Conveyor (OPCC) project is part of continuous expansion of Adaro’s open pit mining operation. The project with US$129-million-dollar capital value and 620,485 direct manhours is to provide crushing & conveying of overburden system at a rated capacity of 12,000 tons per hour. Project scopes are consist of Crushers (2 units), overland conveyors (4 units) along 10 kilometers and RAHCO Mobile Stacking Conveyor (1 unit) along 400 meters and RAHCO spreading conveyor (1 unit) 50 meters boom.

Senior Project and Construction Planner, J Murphy & Sons Limited, Midland Mainline Electrification Project (MMLE-CP5)

T
Tim Adeleye 👤 Member for 12 years 1 month
START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
200
  • Preparing programmes on structural renewals, earthworks, level crossing closure and construction of alternative footbrisges, route clearance etc.
  • Production and monitoring of cost  and resource loaded programme .
  • Production of interface programmes between railworks and other sub/principal contractors.
  • Production of possession programmes, Hr by Hr, ROTR, Site summary programmes etc.
  • Managing programme under NR12(Targeted Cost) form of contract
  • Dealing woth Extension Of Time claims due to ERI's and EWN's

Senior Project and Construction Planner, Downer Edi Engineering, Curragh Mine CHPP Expansion Project, Wesfarmers Resources

START Date
END Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
1000
  • Supported delivery of a new Coal Preparation Plan for Wesfarmers at Curragh Mine in Blackwater ($300m).