Project Planner
Project Planner, BP, NOP
START Date
-
- Develop the Project Planning/Scheduling Controls strategy, plans and procedures, reflecting both BP, (JV) and contractor roles and responsibilities.
- Provide the necessary schedules to ensure the development of proper estimates and studies within a project stage and for sanction.
- Coordinate and/or develop appropriate internal and external schedule benchmarks/technical limits.
- Prepare and implement project wide WBS/CBS, working with the Cost Engineer
- Ensure the preparation and development of appropriate detail and summary project cont
Project Planner, Snamprogetti S.p.A., Qafco 5 - Urea and Ammonia Plant
START Date
END Date
Project Planner: Developing and updating Schedule and Monitoring Procurement Progress and Situation
Project Planner, PPC, Bordolano Gas Storage Plant
START Date
END Date
Bordolano Gas Storage Plant - Bordolano (Italy) - 2006-07 - PPC
Project Planner
Project Planner, Skanska, General Experience
START Date
Pre-Construction Phase
- Creation of a fully Integrated logic linked Master Programme which covers all phases of a project detailing design, procurement and construction activities.