Project Controls Engineer, Transpower, Wairakei C
Implementation of earned value and quantitative risk management processes. Fine tuning of existing cost sontrol processes. Input into set up of contractual payment schedules.
Project Controls Engineer
Implementation of earned value and quantitative risk management processes. Fine tuning of existing cost sontrol processes. Input into set up of contractual payment schedules.
- Directly responsible for the planning structure of the Project.
- Reviews and Approves baseline schedules for awarded packages.
- Works closely with the Client in establishing short programs for summer target and end of year target.
Project Controls Engineer. Main projects and functions:
CCGT Castellón 4 (850 MW, €350 M): Project Controls Engineer.
BCC Tunisia (T&D, €30 M): Project Controls Engineer based in Tunis.
CCGT Santurtzi (400 MW, €200 M): Owner Cost Control Engineer.
Schedule preparation or Thermal Generation Power Plants proposals.
Jan 2007 – Sep 2009 Project Controls Engineer – Bencov Group Ltd
§ Prepare and update detailed work schedules for some of the project’s critical activities like System Pressure Testing Schedule and Plant Shutdown Piping Tie-In Schedule using the Primavera Project Planner.
§ Monitor, quantify and report the work accomplishments, manpower and expended man-hours in my area of responsibility
§ Quantity take-off for progress reporting and billing purposes
I have experience of the full Project Controls service. Providing a planning role on a Substation replacement project, progressing own schedule and monitoring a contractors schedule.
Aslo have responsibilitiy for maintaing costs within budgeted limits. On a mnothly basis produce reports detailing Year to date BCWP / EAC and forecast BCWP / EAC for the financial year and the lifetime of the project.