Project Controls Engineer
Project Controls Engineer
Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), Extension and Rehabilitation of port Jorf Lasfar
i'm working as a planning engineer (project controls Engineer) at Archirodon Overseas N.V Morocco branch. Working in two projects, off-shore sea outfall for a posphat factory and extension and rehabilitaion of Port Lasfar, El Jadida City.
Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), Extension and Rehabilitation of port Jorf Lasfar
i'm working as a planning engineer (project controls Engineer) at Archirodon Overseas N.V Morocco branch. Working in two projects, off-shore sea outfall for a posphat factory and extension and rehabilitaion of Port Lasfar, El Jadida City.
Project Controls Engineer, ANSAQ Contracting Company, Multiple Project - Programs
• Involve in program management, supporting different project managers handling different projects at the same timeline. Develop the schedule management plan and schedule design for the assigned projects, facilitate the development of master construction schedule.
Project Controls Engineer, WorleyParsons, Oil & Gas, Infrastructure, Power
Working currenntly as a Project Controls Engineer with WorleyParsons in Mumbai
Project Controls Engineer, Thiess Pty Ltd, GORGON LNG Project
Project Controls Engineer, Thiess Pty Ltd, Perth Australia
On Gorgon Project at Barrow Island
I have started involving & Learning P6 last few months, found very interesting and challenging.
Updating the program with new WBS / Activities and Progresses on weekly basis to see the actual situation of the project.
Adjust the program (WBSs & Activities) on client priority basis to the restricted manpower on the project
3 weeks, 6 weeks and Look Aheads to Construction Engineers to follow up with the construction activities.
Quanti
Project Controls Engineer, Thiess Pty Ltd, GORGON LNG Project
Project Controls Engineer, Thiess Pty Ltd, Perth Australia
On Gorgon Project at Barrow Island
I have started involving & Learning P6 last few months, found very interesting and challenging.
Updating the program with new WBS / Activities and Progresses on weekly basis to see the actual situation of the project.
Adjust the program (WBSs & Activities) on client priority basis to the restricted manpower on the project
3 weeks, 6 weeks and Look Aheads to Construction Engineers to follow up with the construction activities.
Quanti
Project Controls Engineer, OHL Industrial Perú (Obrascon-Huarte-Lain), Camisea Second Expansion Project
Measurementand control of civil works, programming and project planning activities using specialized software (e.g. Primavera Project Planner P3/P6 and Microsoft Project), assessment of potential delays, cost control, preparation of interim applications for payment and review of subcontractor payment applications and production control.
Pagination
- Previous page
- Page 6
- Next page