Planning Manager

Planning Manager

Planning Manager, Skanska, @One Alliance AMP6

START Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
300

Planner within WRNI (water recycling non infra-structure (sewage treatment works))

Taking schemes from the client as a confirmed 'need'

through 'solutioneering'

detailed design

build on site 

commissioning and testing

and hand back to client 

Planning Manager, St James Homes, The Manor Reading, Worcester Park

M
Matt Orton 👤 Member for 22 years 7 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3800
Experience Hours (Forensic Analysis)
200

Housing estate design procurement and construction planning. Key responsibilities included preparation of schedules, monitoring and reporting site progress along with site setup and logistical appraisal / implementation; preparation of site appraisalsfor new developments / land. 

Planning Manager, Qatar Railways Company, Qatar Railways

H
Hassan Emam 👤 Member for 15 years 8 months
START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
1000

Planning and Controls Manager at Qatar Railways programme. My main duties were linked to Gold Line projects and setting up the PMO processes and procedures

Planning Manager, MMC Gamuda, (EDTP) Electrified Double Tracking Project (Ipoh - Padang Besar) / (KVMRT) Klang Valley Mass Ranpit Transit Project - Underground Works

START Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
1000

·         Develop detailed resource loaded programme based on tender design    documents / general and particular specifications and methodologies

·         Manage and coordinate systems interface planning, databases and providing robust look-a-head forecasts

Planning Manager, Railtrack, Periodic Review

START Date
END Date
Experience Hours (Planning & Scheduling)
3650
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
100

Responsibilities included Developing and maintaining the project plan attached to the project team responsible for the process by which the Office of the Rail Regulator established the financial framework and determined the passenger franchise access charges that effected Railtrack beyond 2001.

Planning Manager, Strategig Rail Authority, Portfollio of projects

START Date
END Date
Experience Hours (Planning & Scheduling)
3650
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
150

Responsible for the development  and surveillance of project programmes within the Programme Management Office. My portfollio of programmes included project programmes for other Directorates detailing how individual Directors / Assistant Directorectors requiements

Planning Manager, Scott Wilson Rail, East London Line

START Date
END Date
Experience Hours (Planning & Scheduling)
1750
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

Reposible for the preparation of programmes required for the Detailed Engineering Phase of TfL's East London Line Northern Extension.