Planning Manager, Sir Robert McAlpine, (various projects)

START Date
Experience Hours (Planning & Scheduling)
1300
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
0

Currently working as Planning Manager at Sir Robert McAlpine, previously completed same role at Grangewood & prior to that Holloway White Allom.

I have experience in general construction but mostly within high end
refurbishment.

Planning Manager, Sir Robert McAlpine, (various projects)

START Date
Experience Hours (Planning & Scheduling)
1300
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
0

Currently working as Planning Manager at Sir Robert McAlpine, previously completed same role at Grangewood & prior to that Holloway White Allom.

I have experience in general construction but mostly within high end
refurbishment.

Planning Manager, Urbacon Contracting & Trading, Head Office

V
victor ruiz 👤 Member for 9 years 3 months
START Date

Assigned at the Head Office Planning Department

Head of the Department for Tender Planning Deliverables

Prepare, Assign, Advise and Check Planning Deliverables for Tender.

Establish Formats for Planning Deliverables for Tender

Create VBA spreadsheet program as tools for planning

Create VBA spreadsheet program to automate reports.

Create VBA spreadsheet program to extract reports data to the database.

Support and advise site planners on various maters.

Planning Manager, Construtora Norberto Odebrecht Ltda., Venezuela, buildings construction, combustible plant, gas compression operation center and recollection systems., PP-PDH integrated petrochemical plant, Refinery, ship pier

START Date
END Date
Experience Hours (Planning & Scheduling)
12500
Experience Hours (Cost Management)
6200
Experience Hours (Forensic Analysis)
5450

Elaboration of proposals for EPC projects (2 years), planning management of earth works to extend a refinery (1.5 year) and of EPC contract to construction of gas compression plants (2.5 years). Change and delay management through contract amendments related to cost and schedule revisions.

Planning Manager, ADtranz Malaysia, STAR LRT Ph 1 & 2, Kuala Lumpur

START Date
END Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Forensic Analysis)
250

Responsible for project schedule development and execution for all E&M (electrical and mechanical) works, both offshore (production, factory testing, delivery), and onshore (installation and commissioning), using Primavera P3. Project scope included 90 light rail vehicles, power supply and distribution, signalling, telecommunications, automated fare collection, workshop and passenger information equipment.