CIVIL / PLANNING ENGINEER

CIVIL / PLANNING ENGINEER, Komuthi Engineering Services , (various projects)

START Date
END Date
  • Preparing monthly work plan using MS Project,PrimaveraPreparing Method Statement and cash flow forecast for the tendering division,
  • Maintain the company rates data for subcontracting items and negotiate with the subcontractors for subcontracted items. 
  • Calling Progress Monitoring Meetings for all sites and circulate the minutes.
  • Represent the company in the meeting with Client, Consultants and Utility authorities.
  • Monitoring the Site Progress Financial Progress  and  prepared the Physical Progress Vs Financial
  • Progress Report to th

CIVIL / PLANNING ENGINEER, Tanmia for Oil & Construction LTD, ADDITIONAL LPG STORAGE & LOADING FACILITIES PHASE 1B PROJECT

START Date

I am Sadeq Al-Baadani, a Civil Engineer Graduated from Sana’a University, Faculty of Engineering and presently working as a Planning Engineer for Tanmia for Oil & Construction Limited, an Engineering, Procurement and Construction Company which has various projects in Yemen, working for TOTAL E&P Kharir Project, Yemen Gas Company and YLNG Balhaf Project in Yemen.

As a Civil Engineer, I can work for all Civil Engineering’s Programs & Ms.

CIVIL / PLANNING ENGINEER, Besix Group Ltd, Cleveland Clinic

START Date
  • Prepare Time Schedules for project (Baseline, Detailed Construction Schedule, Recovery Schedules...).
  • Updating and Progress Monitoring for Project Time Schedules. 
  • Preparation of Daily, Weekly and Monthly Progress Reports for the Client & Senior Management.
  • Assigning all Resources and Cost allocation required in the project.
  • Prepare S-Curve & Cash Flow reports.
  • Support in preparing Claims & time impact.

CIVIL / PLANNING ENGINEER, Al Shafar General Contracting, Souq Residence – Golden Mile

START Date
END Date
  • Prepare Time Schedules for project (Baseline, Detailed Construction Schedule, Recovery Schedules...).
  • Updating and Progress Monitoring for Project Time Schedules. 
  • Preparation of Daily, Weekly and Monthly Progress Reports for the Client & Senior Management.
  • Assigning all Resources and Cost allocation required in the project.
  • Prepare S-Curve & Cash Flow reports.
  • Support in preparing Claims & time impact.

CIVIL / PLANNING ENGINEER, IMECO, Civil Projects

START Date
END Date

Responsibility  :          

 

·         Preparation & Tracking of the Project Master Schedule, Curves & Manpower Histogram.

·         Identification, Monitoring & Streamlining of Critical Paths Running through the Master Schedule.

CIVIL / PLANNING ENGINEER, EC Harris - SEC Corporation, (Dubai, United Arab Emirates), -AlFurjan LLC. Project (2000 VILLAS, Infrastructures, Substations and facilities) , ARABTEC contracting LLC. (Dubai, United Arab Emirates) -AlHekma TOWER (Basment+Gro

START Date
END Date

 

EC Harris - SEC Corporation,  (Dubai, United Arab Emirates)

Period:2007 To 2010

  Projects:  -AlFurjan LLC. Project (2000 VILLAS, Infrastructures, Substations and facilities) , ARABTEC contracting LLC. (Dubai, United Arab Emirates)

-AlHekma TOWER (Basment+Ground+61 Floors) on SH. Zaid Road For HH SH. EYSA BEN ZAID AL NAHYAN.

CIVIL / PLANNING ENGINEER, UKAEA, JET

START Date
END Date

 

The Torus Installation Group is a component of the United Kingdom Atomic Energy Authority. The group is responsible for all operations outside, and supporting those within JET, the world’s largest experimental Fusion Reactor facility. I joined the group as a Planning Engineer after the successful role I played in planning of the 2003 – 2005 In-Vessel Remote Handling Shutdown Operations.

Key responsibilies: