Railway

Siemens Planning Manager

Project Metro Kaohsiung, Taiwan



Developed Programme/Schedule:

E&M Systems Works Programme (Master Schedule, Primavera P3)

E&M Systems Installation Programme for Contractors reference on DWS Development

Coordination Installation Programme (CIP with Civil, Excel)

Track Related Installation Programme (TRIP with Trackwork Contractor, Excel)

Test and Commissioning Programme (Systems T&C / Interface / Systems Integration, Primavera)

Detailed Systems Integration Test Schedule (Hourly Basis, Excel)



Reporting:

Critical Path Analysis

Planning Manager, ALSTOM Transport, Incheon Airport Railway Project

START Date
END Date

Incheon Airport Railroad Project, Korea



Developed Programme/Schedule:

Baseline Contract Schedule (Primavera P3)

Progress Monitoring Tools for Manufacturing & Delivery (Excel)

Progress Monitoring Tools for Installation (Excel)

Track Related Installation Programme (Excel)

Test and Commissioning Schedule (Primavera P3 & Excel)



Reporting:

Monthly Progress Report

Monthly Progress Presentation

Weekly Progress Report

Critical Path Analysis

SAR Transit JV Field Engineer

7018 Lougheed Hwy | Burnaby, B.C V5A 1W2 | Canada



Vancouver Elevated Guideway Project (Millennium Line)-contract value $209M

Inspected works for compliance with contract documents for the construction of 21 Km of elevated guidway including 9 stations.



•     Analyzed specification, and took off quantities

•     Daily coordination of design information from the office into the field

•     Directed and checked sub contractor’s work

SNC Lavalin Segment Manager

SNC Lavalin, Inc. | 1800-1075 West Georgia St | Vancouver, BC V6E 3C9



The Canada Line Rapid Transit Project.



Engineering, Procurement and Construction (EPC) of the Canada Line, an approximately 18 km light rail system with 16 stations linking downtown Vancouver with the international airport in Richmond and Richmond City Center.



•     Prepared budget for Fixed Facilities

•     Prepared project schedule for Fixed Facilities

•     Cost Control

•     Review and tracking of submittals and RFI’s

Carillion Rail Project Manager

Project Manager - West Coast Mainline Track Renewal & Signalling Upgrade Project

Auchengray Level Crossing Renewal - Design & Build

Cleghorn Level Crossing Renewal from Half Barrier to Full Barrier - Design & Build

Cove Crossing - Signalling Upgrade

Reporting directly to Nework Rail as Project Manager on the Civil Engineering & Signalling elements of these projects