Oil / Gas / Power

Senior Planner, Klockner Ina., PVC plant Banda Imam, Iran

START Date
END Date

 

1992:  Klockner Ina., Duisberg, Germany Germany: Senior Planning Engineer

Project: PVC plant Banda Imam, Iran. On and offshore overall project control planning based in Germany. Critical path analysis through the complete sequence: engineering, procurement, shipment, installation and commissioning. Designed WBS co-ordinated with business requirements.

Senior Planner, Filippo Fochi, PVC plant Banda Imam

START Date
END Date

1993: Projects. Banda Imam, Iran:  On-site as member of contract team. PVC plant Banda Imam responsible for on-shore aspects of project control and planning including the civil, mechanical, electrical, instrumentation and commissioning works using Primavera PM software. Successfully instigated the prosecution of large extension of contract claim.

Senior Planner, Filippo Fochi, chloride plant and the Star refinery at Map-ta-Phut

START Date
END Date

1994: Projects in Thailand (with EMCO Ltd):  On-site as member of contract team on numerous petro-chemical and utilities projects. This location included a chloride plant and the Star refinery at Map-ta-Phut and a gas desulphurization power station shutdown (Lampang). Additional duties included Head office tender planning in Bangkok.

Senior Planner, Jacobs Babtie Ltd, Bradwell Power station decommissioning

START Date
END Date

 

2006, March – November:  Jacobs Babtie, UK

Post of project planner for Jacobs Babtie as part of the British Nuclear Group (BNG) programme management team for the decommissioning Bradwell Nuclear power station, Essex, UK.  Using the software tool P3e; specific duties include the maintenance of programme integrity across a multiple project network including the critical path analysis.

  • OCNS security cleared April 2006

CDM Awareness training Sept 2006

Senior Planner System Wide, Sasol, Upstream gas Processing Plant (EPC)

START Date
END Date

 

2009 Jan – 2010 Jan and 2008 Jan – May: Sasol Petroleum International, South Africa

Based in Johannesburg on a consultancy basis to assist in the establishment of high level planning and project controls using the Primavera P6 tool. Specifically, the contract was to realise systematic control of SPI up-stream gas exploration and development project activities in Mozambique and elsewhere, including:

Project Assistant, THOST Projektmanagement GmbH, miro karlsruhe, abb mannheim

K
Kapil Vyas 👤 Member for 15 years 9 months
START Date
END Date

 

THOST Projektmanagement fuer Bauten und Anlagen GmbH (Germany) (www.thost.de)           (Apr 08 – Jan 10)

Project Management Consultant (Trainee)

1)     Client Services

a)     ABB Power Generation