Defence

Senior Scheduling Professional, Boeing Australia, ADF High Frequency Modernisation Program (JP2043) Brisbane, Australia

A
Andrew Dick 👤 Member for 19 years 5 months
START Date
END Date

ADF High Frequency Modernisation Program (JP2043) Brisbane, Australia (Jan 2004 – Jan 2007) Senior Scheduling Professional

  • Responsible for the operation, maintenance and oversight of the project master schedule with primary responsibility for overall schedule integrity; schedule establishment; baseline maintenance; critical path analysis; and identification of potential issues and impacts
  • Providing coverage for the Project Controls Manager during leave of absence; preparation and co-ordination of the Quarterly EAC;

Planning & Scheduling Professional, Boeing Australia, ADF F-111 Weapon System Business Unit Amberley, Australia

A
Andrew Dick 👤 Member for 19 years 5 months
START Date
END Date

ADF F-111 Weapon System Business Unit Amberley, Australia (Oct 2001 – Jan 2004) Planning & Scheduling Professional

  • Responsible for the operation, maintenance and oversight of the project master schedules for the deeper level maintenance of F-111 aircraft
  • Primary responsibility for overall schedule integrity; schedule establishment; baseline maintenance; critical path analysis; and identification of potential issues and impacts
  • Mentoring and tutoring of junior team members; identifying areas for process

Senior Schedulers, Parsons Brinckerhoff (Taiwan), SRP - a project of military base

START Date
END Date

Senior Scheduler of Parsons Brinckerhoff

Schedule Control:

To establish baseline schedule,

To update schedule monthly,

To issue biweekly report,

To do schedule revisions.

Payment:

To set up payment procedure

To establish payment signing forms

To prepare monthly payment for approval

Cost:

To prepare cash flow forecast

Cost & Schedule Analyst, Versar International Assistance Projects (VIAP), 126 Task Orders for Various Military Base Projects Throughout Iraq

START Date
END Date

Monitored, analyzed and generated Limited Schedule Reviews and Analysis Reports on multiple construction projects throughout Iraq for the Air Force Center forEnvironmental Excellence (AFCEE) with a total budget of $4.4 billion dollars funded by MNSTC-I/J7 utilizing Primavera P6 and Pert Master v. 8.1 for risk analysis.