Robertson Construction Group Civil Engineer

N
Nick Brook 👤 Member for 17 years 6 months

Robertson Group (Scotland),

Jan to March 2003, Site Agent.

£8 million Tesco Supermarket.

Supervised the laying of the internal drainage, ensuring its correct and timely completion prior to the ground floor slab pour on a challenging programme.

Following this I co-ordinated the installation of the electrical and mechanical services and plant. This included the design of service routes and the programming of deliveries and works.

March 2002 to Jan 2003, Site Agent.

£4.5 million ‘ring fenced’ Office Block Development at Dounreay.

Mowlem Civil Engineer

N
Nick Brook 👤 Member for 17 years 6 months

Mowlem plc,

March 2003 to Dec 2003, Sub Agent.

£16 million development for BAE at RAF Kinloss to facilitate the arrival of the MRA4 Nimrod.

Responsible for the early completion of £650,000 of renovation works to various ancillary buildings. Following this I was responsible for co-ordinating finishing trades to enable early snagging for a ‘defect free’ handover of a section of the £2m Simulator Building to the client.