Civil / Building / E&M

Senior Planning & Project Control Engineer, Hochtief (UK) Construction Ltd ;Aktor ; Olympia JV Construction, OLYMPIA ODOS Construction

START Date
  • Co-ordination of time schedules with engineers of other departments.
  • Development and preparation of time schedules
  • Collection and collation of weekly and monthly progress data.
  • Verification of progress by inspections/site visits
  • Preparation of weekly and monthly reports
  • Resource loading and resource analysis of time schedule

Senior Planner / Supply Chain Manager / Project Controls, SIAC , AMRAN Cement Plant Project

A
Adel Kader 👤 Member for 17 years 10 months
START Date
END Date

- SIAC ( Egyptian Company )From 15 Nov 1999 till 15 July 2004

a) From 8 July 2003 till 15 July 2004 AMRAN Cement Plant Project In YEMEN - SIAC built the concrete works for a new production line for AMRAN cement plant in YEMEN, it consists of about 42 different buildings such as Preheated, Substations, Limestone Crushing, Gypsum Crushing, Compressor rooms, Silos, Kiln Piers,… with total value 25,000,000 US $

My Duties:

·  Build the time schedule (Base Line Program) and Recovery if required

·  Resourc

SITE ENGINEER, TOMOHAR, TOMOHAR

A
Adel Kader 👤 Member for 17 years 10 months
START Date
END Date

TOMOHAR(Egyptian governmental organization with International Labor Organization ILO) from 6 May 1986 till 31 Jan 1993

a) From 6 May 1986 till 31 Dec 1990 in Construction department as a site engineer

b) From 1 Jan 1991 till 31 Jan 1993 in Training department as trainer of trainers

c) I take many training courses in training department in Egypt, Sweden, Italy, England and Syria.  

Junior Planning Engineer, L*A WTC American Company in Egypt, Water Treatment Plant

A
Adel Kader 👤 Member for 17 years 10 months
START Date
END Date

L*A WTC (American Company)in Cairo from 1 Feb 1993 Till 31 Mar 1994

In head office my Duties:

·  Planning, Time Schedule and follow up the projects.

·  Make Monthly progressing reports.

·  Help in claim section.  

Senior Planner, Technical Office Engineer, Site Engineer at site, Egyptian Arab Contracting, Sanhour, ...

A
Adel Kader 👤 Member for 17 years 10 months
START Date
END Date

- Egyptian Arab ContractingFrom 1 Feb 1995 till 14 Nov 1999

a) From Apr 1998 till 14 Nov 1999 In SANHOUR Irrigation Project, This Project consists of under ground irrigation PVC pipes, Open Block Channels, Small Bridge, Regulator, and Meska Pump Station.