The Data-Driven Approach to Project Risk Management
The data-driven approach to project risk should be:
Talking about Project Management Topics
The data-driven approach to project risk should be:
Hi,
Is a negative schedule variance indicates that the project will not finish on time?
In my opinion NO. because, as of the reporting period, critical items planned values may be achieved and keeping the completion date on time. meantime few non critical activities may not be started on time, keeping the EV less than the PV.
So negative variance only indicates that the value of work done is not as much as of planned.
Share your opinion
Best Regards
Kannan
Hi all,
Any recommendations for a good team management software/application? It must include team management and task delegation and progress features?
apprciated your help
muataz
Hi,
who creates project team and defines the roles and responsibilities of the team? is it the Project Manager? in other meaning who develop RACI Matrix?
best
Hi Experts,
I'm currently looking for what are the best tools or techniques used for airport project construction/Expansion/Renuavation
Kindly suggest me some books or article/blogs which has the following information,
1.Comparision of Project management techniques of different project
2.Tools used for succesful project management in airport
3.Best methods of project management ideas in airport
Thanks in advance
Regards,
Nathan.
Hello there!

I am practicing MS Project 2016 for a construction project in which Activities are as shown in the attached picture.
Greetings,
I am planning engineer, with 2 years exp, i work in a highway project (Site Engineer)
10 months ago, i obtained " CAPM " from PMI in order to widen my project management knowledge
Can you help me with another certificates and/or courses to get in order to develop my career and myself
Any help or comment will be appreciated
Thank You
Hello Everyone,
Just a doubt. Can EPICOR be used for Monthly Reporting for a EPC Project.
Like usually in a Monthly Report there would be,
I do get many of the value working from Excel but some are trying to put the same thing on EPICOR. I havesnt heard much about EPICOR but that is a online platform.
Hi All,
how can i define the project control tolerance criteria for schedule, cost and quality? what is the base?
best,
moutaz
hi all,
what is projects deemed failure?
best,
muataz