Hi All,
how can i define the project control tolerance criteria for schedule, cost and quality? what is the base?
best,
moutaz
Hi All,
how can i define the project control tolerance criteria for schedule, cost and quality? what is the base?
best,
moutaz
for float it does not depened on a project size
for cost it does not depened on size
fro quality it does depend on size and you would have to nornmalize the deficencies basd on the size of the project
thanks Zoltan, my question is: Is there a specific rule depends on the size of the project?
best,
muataz
you can define and set that threshold in terms of float. ie the schedule falls behind schedule by -20 days then a revised schedule will be requested. If the forecasted cost above the budgted amount by X % then a red flag goes up. If the number of deficencies reaches a certain % then a red flag goes up and investigation begins as to what the root cause for the deficiencies is and recommendation on how to correct it.