Customized Report
Hi,
I want a customized report. As a regular stuff..we have activties as lines.
- Read more about Customized Report
- Log in or register to post comments
General planning comments and questions.
Hi,
I want a customized report. As a regular stuff..we have activties as lines.
I was wondering what basic holidays does that include and what is the difference in the calender between a standard 5 day work week and a standard 5 day work week with basic holidays.
Thanks
Dear all,
I'm working on a construction contract where the client are insisting the contract programme should have one calendar. The clients planner has even suggested that the NEC contract requires it to be this way. Has anyone come across this in the NEC as I can not find anywhere calendars are discussed?
My main problem is that I represent the Civils contractor and during the summer months we would normally work 6 days a week 10-12 hrs a day. The default calendar would be 40hrs 5 days a week.
Dear All,
I should prepare an analytical report but have no idea about its content. Doe's any boy have any template for analytical project report?
Regards
Peyman
Hi all,
I am using P6 (v 7.0) and have links to pdf drawings / specs (stored in shared drive) under WP & Docs. I was able to launch all drawings till recently but soon after an Adobe update I get error message saying P6 is unable to find the program that opens it.
[[wysiwyg_imageupload:1027:]]
I can still open the drawings as normal outside of P6 but when I try launching it from P6 I keep getting the error message. Can I somehow assign the default program for P6 to open pdf drawings? ...something like "open with"... Any pointers would be appreciated.
Hi friends,
I am in the planning group of a highway and infra project.Please give your valuable remarks on
what are the major considerations of calculating this project duration when the client
giving us a time period say approx 24 months..
Regards
Sunil
Hi friends,
Currently I am working in a highwayproject.I needs a micro level planning presentation for this project.
Anybody please send me some guidelines for this road project with necessary electrical and drainage works..
your help will be so much for me.
Regards.
Sunil
Dear All ,
Could you please guide me for main Highway activities or sending me detailed sample for high way schedule
Thanks,
Amro
Hi all planners,
I was studying Retained Logic and Progress Override options in P6. And understood well about Retained Logic also I understood that the result under Progress Override are not realistic. Then, the question raised that if the results are not realistic then why this option is there in the P6?, also what is the difference between “Retained Logic” and “Actual Dates” I am sure there lot of experienced planners who can satisfy me.
Cheers