Unassigned baseline problem with current project
Hi All,
Although i havent assigned any baseline to my schedule in bar chart i see baseline bars(project,primary or secondary) for actual activities seen attached picture
When i assign baseline i also see same bars[[wysiwyg_imageupload:1954:]]
Can anybody help me?