Scheduling Activities Just in Time for Its Successor

I have equipment procurement activities that need to be delivered just in time for each install.  I place all the orders on Day 2 of the project.  I want to show, for each equipment, a lead time extending upto its install activity (its successor) starting on Day 3 upto Day X where X varies depending on the equipment. I am using P6 R16.2.  Using the ALAP constraint is an option, but using it for 15 activities? Any suggestions is most appreciated.

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Design Deliverable Planning

S
Shaiju Pv 👤 Member for 10 years 7 months

I have project which consists of quite a large  number of drawings.My cliet asked me to incorporate all drawings in the design and deliverables part of the project. Since i have to link all(majority of ) the drawing to construction part and each drawing will go for  two or three revisions from client how do i link to the construction part .

In short :

1. I have drawings, some of them will undergo 2 reviews,some of them will have 3 or more .

2.In this situation how do we link the drawing to the construction

Thanks and regards,

Shijau

 

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

PrimaveraReader - Viewer for XER schedules

A new way of viewing .XER project schedules exported from Oracle® Primavera P6. It’s a standalone application and offers greater control by providing each member with clear activity insights.

 

PrimaveraReader is a reader for project schedules created with Oracle® Primavera P6. It enables users to open and view project plans exported from Oracle® Primavera P6 in XER or XLS format.  

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

An sterisk on start or finish date

 

Hi All,

 

What does an asterisk shown on start or finish date of an activity mean??

I understood that this symbols comes up when the activity has a constraints date (any kind).

I have received an schedule with asteriks on start or finish dates without any constraints.

Appreciate any input,

Have a nice easter days,

Carmen

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts