Gantt chart and resource allocation

Hi!

The customer requests a layout/view with the gantt chart for the coming month and the resource allocation beneath. (The resources in this case is machinery.) I could almost manage to do this by having the "normal" gantt chart on the upper part of the view and having the activity usage on the information view beneath.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Gantt chart and resource allocation

Hi!

The customer requests a layout/view with the gantt chart for the coming month and the resource allocation beneath. (The resources in this case is machinery.) I could almost manage to do this by having the "normal" gantt chart on the upper part of the view and having the activity usage on the information view beneath.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Creating WBS in MSP

A
Alok Mishta 👤 Member for 9 years 3 months

Can anybody help me in creating WBS for it.

1.que

plumbing, common results for plumbing, schedule of piping, meter and gauges, schedule for piping and pumps, schedule for fixtures, domestic water piping, booster pumps, water distribution, general duty valves, plumbing piping schedule, schedule for equipment, domestic water pumps, HVAC, central cooling equipment, schedules for HVAC, common work results for HVAC, testing, adjusting and balancing, refrigerant compressor, packaged compressor, refrigerant condenser, packaged water chillers 

2.que

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Creating a non splitable task

I have a situation where I have a task of 25 days duration that cannot be split and a shutdown period of one month. What I'd like to be able to setup within Project 2013 is the 25 day task so that it ends no later than the start of the shutdown period or starts no earlier than the end of shutdown period.

I have assigned a resource that does not work during the shutdown period but what happens is that the task starts before shutdown and ends after shutdown (so a 4 week delay in the middle).

Is there anyway to make the task completely jump to after the shutdown period?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Investigating and Addressing Resource Over-Allocation in Microsoft Project

There are numerous ways to handle resource over allocation. The key is knowing how to investigate resource over allocations in Microsoft Project. Here we investigate a few http://ow.ly/AelN307IpS3

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts