Can Main Contractor Insist For A Specific Delay Analysis Method ?
One Year Sub Contracts Works
Finish Date as Per Contract: 31 Dec 2010
Main Contractor Cleared Just 60 % of Area so far , For Sub Contractor works
Complete clearance likely to take 6 more months
Sub Contractor Asked for EOT, Submitted EOT Claim based on “Impacted as Planned “method
Main Contractor Rejects as they require “Time Impact Analysis “
Sub contractor does not have proper progress records but have area clearance dates
Question??
Can Main Contractor Insist for a specific analysis method??