Can Main Contractor Insist For A Specific Delay Analysis Method ?

One Year Sub Contracts Works

Finish Date as Per Contract: 31 Dec 2010

Main Contractor Cleared Just 60 % of Area so far , For Sub Contractor works

Complete clearance likely  to take 6 more months

Sub Contractor Asked for EOT, Submitted EOT Claim based on “Impacted as Planned “method

Main Contractor Rejects as they require “Time Impact Analysis “

Sub contractor does not have proper progress records but have area clearance dates

Question??

Can Main Contractor Insist for a specific analysis method??

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

DELAY TO START THE WORK

Dear Sir,

I need to know which kind of notice I will give to the Engineers and Client If I cant start the work on the given date due to documents approval. For Delay in Completion I know I can give Notice of Extension of Time but Delay to Start the work, I dont Know. I read their Condition of Contracts but its not there.

PLEASE ADVICE

Regards,

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

When should be the data date/cut-off date for Impact Programme

The contract completion date for our project has already passed. But due to some delays (our own delay and client's delay) and additional works (which cannot be linked to any of the contract works since these are independent to the original scope), we haven't finish the project yet. I was asked to make an impact programme to show the delays we encountered and the probable completion date of the project. My question is, when should be the data date for the impact programme? At the original contract completion date? At the latest update of the baseline programme?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Claims based on specifications

good morning to all planners in the world 

There is condition in the specification in the contract, forced us to submittal inspection request to anything to QC department of supervisor before 24hr, for example if we want to submit inspection request to casting blinding concrete for specific area we must submitted before 24hr from casting. can i used this condition as one of reason of delay in project

 

please advice

best regards

jihad aldaoud  

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Delay Analysis or Time Impact Analysis (TIA)

Hi Planners,

 

I need your advise for this matter. The Contractor has been lapsed for their Contractual completion date but the project remain incomplete (XX% complete) which difinitely requires Extension of Time to complete the outstanding works. The delay is a direct results of Force Majeure including delay matters from both Contractor and Owner. Consequently, Contractor applies for an extension of time, but no level III program has been submitted. They intent to submit the program upon approval of the 1 year EOT.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

disputs resolution ,amicable settlmet ad arrbitratio proceedures

dear all

 

due to finanncial crises many projects were adversaly affected due to shortage of payments and may clients had delayed the payments for the over due payments.

 

we used to go through the disputs resolutio , amicable settlment ad arribtration process.

 

can ayoe give us the best practice related to the above .

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Comment on Forensic Schedule Analysis Recommended Practice

P
PP Admin 👤 Member for 17 years 4 months

Dear Members,

We have been asked by the Association for the Advancement of Cost Engineering (AACE) to see if you are interested in providing possible revisions to the AACE International Recommended Practice Forensic Schedule Analysis Practice Guide.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Imposition of milestones within NEC Option C

N
Neil Coker 👤 Member for 15 years 7 months

We have a situation where we have been instructed to accelerate works to meet a new milestone date but the Client has specifically noted that the Key Date has not changed (the Key Date is next year and the new milestone is before Christmas this year). In addition, this has not been instructed under Cl 36 "Acceleration"  but under Cl 60 "Compensation Events" . As defined under Cl 61.1 we have started the work and issued the quotation and programme to the Client.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts