KEO INTERNATIONAL CONSULTANTS

PLANNING ENGINEER, KEO INTERNATIONAL CONSULTANTS, Hamad Bin Khalifa Medical City

START Date

Works as Planning Engineer (PM-CM and supervising consultant) for the Hamad Medical City Project in Doha, Qatar. Responsible for overseeing and providing planning advice with regard to critical schedule milestones on one of Qatar’s most prestigious projects. Generating milestones in the pre-construction stage for inclusion in tender documents via detailed discussions with the Design Manager, Design Team, and other participants. Monitoring, adjusting and updating the cost plan and cash flows and the consolidation of these results in weekly reports.

John Campillanos

First Name
John
Last Name
Campillanos
Professional Since
Oldest experience
Years Experience
42
Telephone Number
+97466686949

Seventeen (17) years of experience in high rise 23 to 48 floors residential, commercial, hotel and mixed use buildings. Medium rise 2 to 5 floors commercial, schools and hotel buildings. FINA standard Aquatic Center, Expressway Roads and Bridges Construction and Infrastructure works in the following field and position:

Planning & Project Control Manager, KEO INTERNATIONAL CONSULTANTS, SIDRA Medical & Research Centre

START Date

Responsible for all planning aspects, programming and progress control of the project, ensure that all project submissions, approvals, procurement, and Milestones are met. Monitoring and following up the project progress, and ensure that all potential delays and risks are addressed and dealt with in appropriate manner.

Liaise with the client and contractor to review and agree the project progress.

Manage micro programmes when required to ensure the delivery of the projects

Senior Planning Engineer, KEO International Consultants, A’ayan Tower project

START Date

Mr. Al Roumani is responsible for developing the Project Master programme, reporting to the Client, evaluating Contractor’s programme and progress, assessing time claims, preparing risk registers on weekly basis, proposing packaging strategy/schedule to the Client.

Time and Cost Engineer, KEO INTERNATIONAL CONSULTANTS, Al Tijaria Tower

START Date
END Date

Time and Cost Engineer, May 2007 – May 2009

During Mr. Al Roumani time as Time and Cost Engineer, his responsibilities were:

Evaluating the Contractors schedule, updates, payments, delay, counter claim. Preparation reports to theClients, evaluation of Contractor's claims (Time).

Various projects, including: 

Senior Planning Engineer, KEO INTERNATIONAL CONSULTANTS, Convention Center Extension

START Date
END Date

Senior Planning Engineer in the Education City – Convention Center Extension project in Doha - Qatar, Mr. Al Roumani is responsible for preparing reports for the Client, evaluating Contractor’s programme and progress, preparing risk register and reviewing and assessing Time claims.