Assistant Project Engineer, Cekap Technical Services Sdn Bhd, 1. Detail Study of FMECA for PM323 & PM 329 for SKE 2. Provision of Bathymetric Survey for Dredge Navigation Channel

A
Arif Sazali 👤 Member for 9 years 8 months
START Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

My roles & responsibilities involve planning, and monitoring on project execution, resource, and contract management as per following:

• Strategic planning which includes setting up project goals, identifying project
deliverables, setting up project milestones and develop projects tasks.
• Resource planning that includes establishes responsibility matrix and man-hour loading
for labor resource and strategize requirement and requisition plan for non-labor
resource.
• Establish and execute procedures and guideline for contractual management throughout the
whole projects.

Arif Sazali

A
Arif Sazali 👤 Member for 9 years 8 months
First Name
Arif
Last Name
Sazali
Professional Since
Oldest experience
Years Experience
4
Guild Accreditation
Awaiting Applicant
LinkedIn Profile
in/arif-sazali-b989aa3b

An overall experience of 4 years in Oil and Gas in Project Management, and Contract Management that includes Planning, Execution, and Monitoring. Good exposure in, PETRONAS Project Management System, Petronas HSEMS, EPCIC, FMECA, and Bathymetric Survey. Having a positive can-do attitude with good work ethics, I am seeking better opportunity to involve more in the technical aspect to improve my knowledge on the respective area.

PROJECT ENGINEER, Cekap Technical Services Sdn Bhd, 1. PMC for Zuhal East Development Project 2. PMC for Development of Layang Wellhead Platform

A
Arif Sazali 👤 Member for 9 years 8 months
START Date
END Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

Area of Experience: Contract Management For some project, I am responsible for the contractual management and administration of the project which includes the following: • Establish standard procedures and guideline that conform to the project terms and conditions. • Execute & manage contracts entered into with vendors and contractors to uphold to the project and company’s term and conditions. • Provide administrative support to the project team and support team which includes project meetings and travel arrangement, general procurement activities.

PROJECT ENGINEER, Cekap Technical Services Sdn Bhd, 1. Detail Study of Failure Mode, Effect and Crtiticality Analysis for PM323 and PM 329 for SapuraKencana 2. Provision of Bathymetric Survey for Dredge Navigation Channel and Basin

A
Arif Sazali 👤 Member for 9 years 8 months
START Date
END Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

 CEKAP TECHNICAL SERVICES SDN BHD (August 2012 – Ongoing) Position: Project Engineer My roles & responsibilities involve planning, and monitoring on project execution, resource, and contract management as per following: · Strategic planning which includes setting up project goals, identifying project deliverables, setting up project milestones and develop projects tasks.