Tube Lines (Bechtel and Amey / Ferrovial) has won a 30-year concession of London Underground’s Jubilee, Northern, and Piccadilly lines under the PPP/PFI, to improve and maintain the infrastructure of these lines. Bechtel is responsible for the Capital Works Program, whilst the Maintenance Program is led by Amey / Ferrovial.
My roles are the following;
Responsible for supervision of cost engineering activities for the Prorgamme Office.
-
Monitoring the budgets, commitments and actual costs (GBP 76M).
-
Preparation of detailed staffing plans, budgets and estimates for the Programme Office.
-
Responsible for preparation of financial status
reports; Project Financial Status Report (PFSR)
and Project’s Cash Flow.
-
Collection, monitor, review cost data files and
labour estimates and currency hedges.
-
Interface with Bechtel Accounts and Treasury for financial monitoring.
Collection, monitor, review cost data files and labour estimates and currency hedges.
Responsible for preparation of financial status reports; Project Financial Status Report (PFSR) and Project’s Cash Flow.
Adaptation of the Project Controls University for a Tube Lines’ environment.