A 408 km pipeline is being constructed to a new LNG plant of the coast of Peru. ISI Solutions will provide the EPC if the Telecommunications and SCADA System along the pipeline (14 Valve Stations, Main and Secondary Station 4 Pressure Control Stations).
Main Responsibilities are:
-
Monitoring the Project’s budgets, commitments
and actual costs.
-
Preparation Cash Flow ands staffing issues.
-
Collection, monitor and review cost.
-
Preparation of Invoicing.
-
Communication with client on project issues.
Significant Achievement: I have set up the Trend Program for this project with the idea of extending it to other projects. Helping in setting up a Project Financial Report.