Project Manager, Wellstream GE, Albacora Sapinhoá e etc, All, Caratinga, Lula, operated by Petrobras (Wellstream), Risers / Flowlines fabrication and onshore/offshore services for the following basis: Piranema

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
600

Project Management  - Project Manager, May 2010 – October 2012

Project Manager of Flexible pipes manufacturing and onshore/offshore services, in charge of managing the project execution phase after the contract issuance, holding the Kick-off meeting with all the areas involved and following up the scope, time and cost activities with the project indicators, from the detailing engineering to the Load out. I also made the interface between the client and internal stakeholders, such as Engineering, Procurement, Manufacturing, Quality, Logistics, etc in accordance to PMBOK, T & C of the Contract and company goals and strategies.