START Date
END Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50
An $80 million medical facility project. OnTrack created the initial baseline schedule based on architectural drawings. Then we worked with the Owner, Subcontractors and General Contractor using Reverse Phase Scheduling to achieve a consensus on milestone end dates.