Planning & Project Control Engineer, ENERGY WORKS TECHNOLOGY LIMITED, TOTAL EGINA UFR PROJECT (OIL & GAS)

START Date
END Date
Experience Hours (Planning & Scheduling)
30000
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
50

Image removed.         Responsible for Project Planning and Scheduling of Engineering, Procurement and Construction of Structural Project with computerized systems Primavera P6.8.3 or Microsoft Project.

Image removed.         Develop & Implement Project Control Procedures / Change Order with Project Scope of Work.

Image removed.         Update schedules with physical progress and man-hour expenditure to show all trends, status, and forecast & prepare scenarios.

Image removed.         Ensure the Overall Planned Project S-Curve against Actual Project S-Curve isusually updated monthly.

Image removed.         Prepare & present all weekly and monthly progress reports to Senior Management & Contractor.

Image removed.         Supervision and Coordination with team of engineers and designers.

Image removed.         Coordinate with the Quality control department as well as the Client for inspection of the fabricated joints.

Image removed.         Highlight critical activities and other constraints to Management.

Image removed.         Follow up Review of Shop drawings for structural and piping drawings.

Image removed.         Conduct weekly status review meetings with Contractor

Image removed.         Monitoring the progress of the project at different stages of its development

Image removed.         Making sure the achieved progress on the project fits the progress anticipated in the schedule.

Image removed.         Review schedules and planning ensuring that it’s according to contractual weight factors.