Planning & Project Control Engineer, SAMSUNG HEAVY INDUSTRIES (SHI) NIGERIA, TOTAL EGINA FPSO PROJECT

START Date
Experience Hours (Planning & Scheduling)
30500
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

Image removed.         Responsible for Project Schedule Update and Change Implementation of Six (6) Structural Modules with Primavera P6. 8.3.

Image removed.         Implement Charges on Project Control Procedures with Project Scope of Work.

Image removed.         Update schedules with physical progress and Man-hours expenditure to show all trends, status, and forecast & prepare scenarios.

Image removed.         Ensure the Overall Planned Project S-Curve against Actual Project S-Curve isusually updated monthly.

Image removed.         Prepare & present all weekly and monthly progress reports to Senior Management and Client.

Image removed.         Highlight critical activities and other constraints to Management.

Image removed.         Monitoring and reporting of the progress of all aspects of the Project (Engineering, Procurement, Construction and Commissioning, Contractual, etc…).

Image removed.         Follow up Review of Shop drawings for structural and piping drawings with team of Engineers/Designers.

Image removed.         Conduct weekly status review meetings with Client.

Image removed.         Monitoring the progress of the project at different stages of its development

Image removed.         Making sure the achieved progress on the project fits the progress anticipated in the schedule.

Image removed.         Review schedules and planning ensuring that it’s according to contractual weight factors.