Scheduler, Contract Solutions, VA Hospital

START Date

Project Scheduler

Hoffman Construction

January 2011 – August 2011 (8 months)Hillsboro, Oregon

*Fast paced environment to schedule the construction of a $3 billion dollar project

*Managed and directed meetings to follow agendas

*Critically analyzed workflow logic to develop solutions for time constrained problems

*Helped team members with computer questions

 

Image removed.

Project Scheduler

Skanska USA Building Inc.

June 2008 – August 2009 (1 year 3 months)

*Assisted general contractor Skanska efforts to manage sustaining work for Intel

*Sequenced activities using logic to create critical paths

*Resource loaded schedule activities to prevent trade stacking

*Enhanced ability to create a schedule from design drawings

*Worked closely with trades to increase construction knowledge

*Helped Skanska achieve all of Intel's major schedule milestones

*Attended Skanska University classes to broaden project management knowledge

 

Image removed.

Project Scheduler

Haskell Corporation

September 2007 – December 2007 (4 months)

*Helped subcontractor Haskell construct mechanical portion of an REC plant

*Learned how to create a real-world, logical schedule

*Assisted project control manager by developing project schedule scenarios

*Updated and analyzed schedule to define critical activities causing delay

*Taught to scan construction site in order to predict construction interruptions

 

Project Coordinator

Technogym USA

2006 – 2007 (1 year)

• Coordinated product training sessions throughout the United States

• Managed accounts

• Developed strong phone skills

• Learned business-to-business sales methods