Planning Engineer, MunaiGazKurylys LLP (MGK) (Aktau, www.mgk.kz), Plant Firewater Upgrade Project

START Date

• Drawing-up relevant network installation activities schedule in Primavera 6; 

• Drawing-up S-curves based on a relevant schedule/resources built-in Primavera 6. Respective forecast plotting (in the form of S-curves) in case of any deviation from project execution plan upon Client’s request; 

• Linear-calendar construction activities bi-weekly schedule preparation and update on a weekly basis; 

• Required on site man power monthly planning with consideration for all deviations from the targeted schedule; 

• Weekly completed activities progress per S-curve update for the Client; 

• Completed activities progress update in P6; 

• Completed site activities daily report draw up; 

• Completed site activities progress weekly report draw up; 

• Project execution analysis, incorporating all constraints for construction, various type reports preparation according to Management’s requests.