Kitimat Modernization Project400.000Tons/year Aluminum Smelter on Kitimat, BC for Rio Tinto Alcan.
Senior Plannerfor Pre-Feasibility & FEED studies, Early Works (Cleaning&Demolition, BrownField works, prep works) and Construction Works
Master and detailed schedules (level 1 to 5), March Charts, Line of Balance schedules. Resources loaded schedule level 3 in Primavera 6, WBS, critical paths analysis, progress & resource curves, comparative installation curves, schematic schedules, Primavera Risk Analysis. Contracts & Procurement schedules for major equipment and long lead items