July 2015 to June 2016: The Engenda Group, Runcorn, Wirral.(MMC Management)
– Senior Planning Engineer
- Working on a £7.5m boiler strip out, fabrication and re-fit on the Fellside Boiler Park Project, Seascale, Cumbria. This project is managed under NEC 3 Option A.
- Production of WBS, OBS and CBS structures to enable a programme build covering strip out works, fabrication of new pipework and supporting steelworks prior to onsite installation and commissioning.
- Monitoring workshop based pressure on individual pipework sections built to ISO’s approved for construction.
- Liaising with sub-contractors to bottom out the full scope of Electrical works including cable pulling, installation of Free Issue Electrical Equipment.
- Producing Cost profiles, EV Reporting, CPI AND SPI monitoring