START Date
END Date
JANUARY 2008 – APRIL 2009
Company/Institution: Shaw International Ltd
Home Office: 21 st Al Moosa Tower II, Sheikh Zayed Road, Dubai
Plant place: SANMEN ,HAIYANG
Project: SANMEN 1 & 2 Nuclear Power Plants
HAIYANG 1 & 2 Nuclear Power Plants
Work Office: Shanghai
Country: China
Position: CI/BOP Schedule Supervisor
Duties:
- Monitor schedules to identify trends and takes proactive measures to maintain progress.
- Monitor cost to identify trends and takes proactive measures to control costs.
- Develop and manage a contract change control program for the project.
- Develop and manage the Level 1, Level 2 and Level 3 Integrated Project Schedule.
- Prepare Exception Reports, showing the comparison between original
and current plan, analyze potential impacts and recovery plans as
needed
- Critical Path Analysis and schedule risk analysis as needed.
- Prepare milestone reports
- Analyze category A1, A2, A3, B &C equipment procurement delivery
schedules
- Develop the format and requirements of the schedules and institute the
processes and procedures to implement and update these schedules for supporting the various sub-organizations of the project by providing a structure for expected inputs and frequency of updates
- The Level 3 schedule, the 3 month rolling schedule and the detail
schedules for the BOP primary equipments
- Work process development and analysis
- Root Cause Analysis
- Development of Bulk Curves
- Calculation of Earn value for engineering
- Calculation of Earn value for procurement
- Calculation of Earn value for construction
- Development of S earn value curves
- Interpretation of curves and analysis
- Recovery plans
- Forecast plan
- Engineering and procurement planning and scheduling
- Construction planning and scheduling general logic
- Construction civil scheduling
- Construction piping and mechanical scheduling
- Construction electrical and instrumentation scheduling
- Start up and commissioning scheduling