A new station building with an integrated footbridge linking to three platforms and other rail infrastructure to be used by around 3,500 passengers a day. The extension of the Busway from Milton Road to the station as well as linking to the new town of Northstowe. · Works Included new OLE gantries, new P.Way and slewing of existing P.Way. · My Duties as Project Delivery Manager (Ilford) was to take the lead operationally ensuring 6 weekly programmes are completed; oversee the main program, selection of subcontractors, liaising with Crossrail and various stakeholders such as NR, Albelio and Bombardier. · Ilford Depot scope of the works includes design, procurement, installation, testing and commissioning of the new sidings, accommodation building and major modification of other existing depot facilities.
Project Delivery Manager (CRE), Volker Fitzpatrick, Cambridge North Station
START Date
END Date