TIANQI LITHIUM PROJECT: New Greenfields Lithium Hydroxide process plant in Kwinana.
Consultant for Tianqi Owner’s team.
- To write detailed Primavera Construction and commissioning schedule for Train 1 & 2.
- Work with Turner & Townsend team of Quantity Surveyors and transpose measured quantities to completion for piping and electrical so that schedule balances with measure at all unit of measure levels.
- Introduce global coding structure for all Tianqi projects. Key global code being Commodity code structure to define coding all units of measure.
- Build complete Construction and commissioning schedule that is fully resourced with all units of measure, manhours and cost.
- Intergrade Primavera commissioning schedule with Siverhorse commissioning software for automated progress reporting.
- Determine means, procedures, schedule logic, true critical paths to reduce project slippage.
- Revise Commissioning sequence to overlap remaining construction with commissioning.
- Convert Aconex Drawing data to P6 and automate Aconex to P6 drawing updates until Redline drawings complete.