Forensic Planner / Delay Analyst, SINCLAIR KNIGHT MERZ - SKM, Dampier Fuel Warf Project

START Date
END Date
Experience Hours (Forensic Analysis)
250

Dampier Fuel Warf Project Marine & Piping Expansion Project in Dampier.

Forensic Planner, (Specific Assignment), 08/2011 to 10/2011

EOT Defense review for owner against construction contractor due to drawing delivery delay and access delay.