Project Planner, Skanska, Central Nottinghamshire PFI Hospital

START Date
END Date

 

Redevelopment of Kings Mill Hospital, Mansfield Community Hospital and provision of services at Kings Mill Hospital, Mansfield Community Hospital and Newark Hospital.

§         Working in planning team that examines project issues to identify issues related to the project completion.

§         Generate reports and charts from P3 for management level submission.

§         Periodic updates of the project and Store Period Performance for the financial periods.

§         Responsible for monitoring and updating the target plan of 5000+ activities and also a client (NHS Trust) plan of 400+ activities.

§         Checking and altering the relationship links between activities and also creating new link for certain activities to place them within the target completion date.

§         Assigning resources for individual activities and generating Summary Resource Assignment Reports to create chart with Units spread of the project period.