Planning Engineer, ABB, JG Summit PE Capacity Expansion Project

START Date
END Date
Experience Hours (Planning & Scheduling)
2300
  • Develop and forecast project schedule to achieve contract completion
  • Monitor material shortage at site
  • Submission of weekly Project Progress Report and highlight area of concerns
  • Claim of Monthly Progress to client with supporting document and photos
  • Review subcontractor’s Progress Claim
  • Monitor completion amount versus Contract amount