·Aug 2012 – Actual COEG - Rnest. Ipojuca -PE, RJ
Planning Coordinator
Poli pipelines 7 km diameters 8 to 46 inches conecting the port to Petrobras refinery cerca US$400 million project
Coordination of Plannig team
Measurement analyses
fisical and finacial curve Follow up
Follow up of manpower and equipmen schedule
Forecast reports.
·Oct 2011 – Aug 2012 Lyon Engenharia. Paracatu,MG
Planning Engineer
In a Management of works contract with Kinross gold corporation accomplish this activities:
Planning coordination.
Execution and update of physics and financial curves.
Execution and update of man power/equipment schedule.
Execution and update of Schedule.
·Mar 2011 – Oct 2011 Multitek – COMPERJ. Itaborai, RJ
Planning Engineer
In a Civil works, owner is Petrobras accomplish this activities.
Measurement Report documents analyses.
Execution and update of physics and financial curves.
Execution and update of man power/equipment schedule.
Execution and update of Schedule.
Execution and update of WBS.
Execution of Works Daily Report.
Coordination of planning department.
· Feb 2010 – Mar 2011 Le Chocolatier . Vitoria, ES
Executive Director
Work in my family chocolate factory, abot 50 employees accomplish this activities:
Production procedures analysis;
Development of new products;
Custs Analysis;
· Jun 2008 – Jan 2010 Conduto – Cia Nacional de Dutos. Feira de Santana, BA
Planning Engineer
In a 28” Gas pipeline works, owner is Petrobras accomplish this activities.
Measurement Report documents analyses.
Execution and update of physics and financial curves.
Execution and update of man power/equipment schedule.
Execution and update of Schedule.
Execution and update of WBS.
Execution of Works Daily Report.
Management of department in reason of health license of the manager.
Order and quotation of Electrical and instrumentation Works material.
Coordination of electrical material receive procedures.
Inspection of assembly of electrical and instrumentation acting as Electrical Engineer.
· Jun 2006 a May 2008 Sinopec International Petroleum Service. Vitória, ES
Planning Tecnician
Measurement Report documents analyses.
Execution of physics and financial curves.
Execution of man power/equipment schedule.
Execution of update of Schedule.
Execution and update of WBS.
Support in coordination of electrical and instrumentation Team.
· July - August, 2004 DaimlerChrysler do Brasil Ltda. Juiz de Fora, MG
Trainee Program
Maintenance commissioning in the final and crude assembly.
Studying the new “Industrial Control Station” aimed at line adequacy.
Studying the new “Industrial Control Station” aimed at new operating system.
· June - August, 2003 CST – Estel Máquinas e Serviços. Vitória, ES
Trainee Program
Development and correction of electrical maintenance standards.
Documentation of improvement proposals.
Development of presentations for internal courses.
· January – April, 2003 Hochschule für Technik Wirtschaft.Dresden, Germany
Trainee Program
Study of programming language “G” (LabView).
Development of ‘Virtual Instruments’ with pedagogic purpose.
· June – July, 2002 Invesys / Foxboro – Aracruz Celulose. Aracruz, ES
Practice
Commissioning on implementation of the cellulose plant new line.
Commissioning in cellulose plant boiler I/O changes from analog to digital.
Education
· 2006 Universidade Federal de Juiz de Fora. Juiz de Fora, MG
Electrical Engineering
IT knowledge
Internet, Office, Flash, Autocad, MS Project, Primavera P6, Mantain, Assembly, LAN, Lab View, SAP .
Mastery of IT in advanced level.
Languages
1. English – advanced level
2. Spanish – advanced level
3. German – basic level
4. Portuguese – native speaker