Foster Wheeler, Khabarovsk, Russia April 2013 to now
Project Controls
OJSC Refinery plant, based in Russia. 3.6 million Mhrs to go. System Schedule and delivery systems to rebuild.
Technip Russia, Nijni Novgorod, Russia April 2012 to April 2013
Planning Manager
IKRA PVC plant, based in Russia, 12 million Mhrs. Primavera 6 Lev3 Schedule developed with resources, Mhrs and quantities. Progress measurement system carried out by CPMS program. Lev4 Primavera 6 developed by process building. Reporting: on a weekly and monthly basis. Sub-contracts scheduling control. Pre-commissioning and commissioning Primavera 6 System Schedule under develop.
Tecnicas Reunidas, Chile and Bolivia January 2011 to Mar 2012
Project Controls Manager
Margarita Gas Plant, based in Bolivia, 2 million Mhrs.Executing the planning and control of the gas plant and internal pipelines. Primavera 6 Lev 3 Schedule developed with resources, Mhrs and quantities. Utilizing progress measurement systems. Lev4 Primavera 6 developed by building and packages. Reporting: on a weekly and monthly basis. Sub-contracts scheduling control. Test Packs control system developed and followed up. Pre-commissioning and commissioning Primavera 6 System Schedule.
GIS Engineering, Argentina November 2010 to Dec 2010
Planning Coordinator
Planning of the biggest Milk Farm project in Durazno, Uruguay during the phase of engineering and purchasing.
Technip Polska, Poland July 2009 to Aug 2010
Planning Coordinator
PMC team for the 10 Plus Gdansk Refinery project. Subcontractor schedules and progressing control. Progress curves updating on monthly basis. WBS quantities control. Spools and welding Inches diameter schedule and follow up. Test Packs control follow up.
Technip, Qatar March 2007 to March 2009
Field Planning Engineer of Utility Area and Inlet.
LNG QGX Project based in Qatar. 250 million Mhrs. Primavera 3 Lev3 Schedule developed with resources, Mhrs and quantities monthly updating. Sub-contracts scheduling control. Spools and welding Inches diameter schedule and follow up. Test Packs control follow up. Pre-commissioning and commissioning Primavera 3 System Schedule updating monthly. In charge of the follow up the Tie ins with to other plants of the Ras Lafan industrial city. Level 4 schedule of Turbines packages follow up. Involved in the planning and control of the Tanks and jetty area.
Snamprogetti, United Arab Emirates July 2005 to December 2006
Project Controls
Responsible for Reporting and Scheduling of the BuHasa Facilities Upgrade project. Including the increasing of the injection capacity (oil & gas) and update the processing units in order to obtain 730.000 BO/day.
BP, Argentina August 2002 to July 2005Project Coordinator
Responsible for coordination of the Energization Project at Golfo San Jorge, including installation of 7/12MW gas turbines, 10 Substations 33/13,2 KV, and 1300 km of medium voltage power lines. Provided powered to 1700 wells.
BP, Argentina August 2001 to July 2002
Project Controls Engineer
Responsible for planning and control of upstream projects (gas pipelines, power generation, distribution, automation and gas re-injection, compression, buoy/SPM) in Chubut, Argentina.