Planner/Scheduler, WorleyParsonsCord, (various projects)

START Date
END Date
  • Developed and maintained detailed project schedules on a weekly basis.
  • Prepared weekly forecast data update commodity curves, resource histograms and progresscurves.
  • Facilitated the cost forecasting process for the monthly management report.
  • Developed and maintained the Direct and Indirect Labour staffing.
  • Developed and maintained the Indirect Labour staffing plan.
  • Liaised with superintendents to monitor progress and performance for all disciplines.
  • Monitored subcontractor’s progress and performance to ensure adherence to the master schedule.
  • Provided ongoing support to continuously improving Project Controls at the project and corporatelevels.