West Qurna II, Mishrif Full Field Project, Iraq.
Ø Develop and maintain Level 2 Project schedules based on the provided scenarios based on the approved WBS
Ø Develop S-curve for different scenarios to support decision making
(Progress and Milestones)
Ø Analyze, report and suggest potential impacts and preventive actions of project schedule risks
Ø Regular reporting of project current progress status and forecast
Ø Develop and maintain Project progress logs
Ø Ensure Project Control procedures are observed and updated throughout the project life cycle
Ø Consolidate Asset Work Program on a weekly basis
Ø Supervise team of 5 planners
Ø Monitor Contractor during development of Level 3 and Level 4 schedules to avoid potential progress delays
Ø Ensure baseline schedules are frozen within time limit specified in the contract
Ø Identify conflicts between various schedule elements and advise Project Management of their potential impact
Ø Improve Schedule quality
Ø Produce overall schedule overviews for the Project Management