Cost Loading at Late Stage of Project
Forum TopicHi all,I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculat...