Search

Cost Loading at Late Stage of Project

Forum Topic

Hi all,I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculat...

Sep 21, 2016

Resource load levelling within multiple projects

Forum Topic

Hi all,I have a query relating to load levelling resources within multiple projects with differing priorities.I know a project has a "Project Levelling Priority" function within P6, so you can level using "Level Resources" that way; however, my sched...

Sep 21, 2016

How can I see planned AND remaining work in the same report?

Forum Topic

If I am running a cost loading report out of a status project, for the purposes to inform my customer what unfinished work is remaining on the project, and how it is time phased, I am only seeing BCWS.  The remaining work of the in progress activitie...

Sep 21, 2016

Resource usage profile chart not displaying correctly?

Forum Topic

Dear all,sorry i am newbie in P6 and just doing some self study.i am having some prblems with regards displaying the actual resouces used in my project. i have assigned the planned and actual resources on each activity but when looking ant the resour...

Sep 22, 2016

planning engineer - other name

Forum Topic

Hi,Am currently working as a junior planning engineer in UAE, I plan to immigrate canada. I just went through the job bank of canada, I could not find the job posts for planning engineer.I need to know is there any other name for planning engineer?

Sep 22, 2016

planning engineer - other name

Forum Topic

Hi,Am currently working as a junior planning engineer in UAE, I plan to immigrate canada. I just went through the job bank of canada, I could not find the job posts for planning engineer.I need to know is there any other name for planning engineer?

Sep 22, 2016

Resource leveling in PRA

Forum Topic

Hello planners,Where could I find some comprehensive documentation about the nudge and resource leveling process in Primavera Risk Analysis?Having tried to level the same project in P6, MS Project, Spider and finally PRA, I find that PRA does not res...

Sep 22, 2016

Activity Delay in p6

Forum Topic

Hi every onecan  Actrivitiy Has a delay in days more than the Updating interval ex.: if th update Int.=30daysafter update can the activity has more than 30 days delay greater than the previous delay ???

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016

Test Exam Integration

Page

EXPERIENCE REQUIREMENT The provision of an Experience Profile to show ~ 1 years of work relevant the the Credential (i.e. about 2,000 hours).  Project Controls (as opposed to Planning or Cost or Claims) applicants will need to demonstrate an appropri...

Sep 22, 2016

5 Annual Objectives for PMO Leaders

Forum Topic

You might be wondering why we’re focusing on annual objectives right now, when typically you’ll see articles about goal setting at the start of the year. It’s because now is a great time to be reflecting on objectives and making sure that you and the...

Sep 23, 2016

Create P6 resources dictionary using excel without using SDK

Blog

The SDK (Software Development Kit) is an awesome tool that allow P6 database to connect to excel and exchange information in order to create the schedule using excel. But sometimes the SDK is not installed on the Primavera machine and the scheduler d...

Sep 23, 2016

Resource Distribution Doesn't Work Correctl, Any Idea?

Forum Topic

Hello,I was trying to check an activity's resource distribution from Resource Assignments tab but eventually I realised that eventhough I increased the remaining time of that activity, the distribution of resource doesn't change. It only shows exact ...

Sep 24, 2016

CAREER ADVICE

Forum Topic

HELLO EVERYONE, I have recently comleted B.TECH IN INSTRUMENTATION ENGINEERING in India. Would it be wise to start off  my career as Planning engineer?? Do planning engineers in instrumentation field have good scope for career advancement?

Sep 24, 2016

Can we avoid project delays caused by bad weather?

Blog

Has your project been delayed by bad weather? Contractors are an eternally optimistic bunch and never seem to allow for any weather related impacts on construction projects. What, - are you really going to work on a twelve month long project and thin...

Sep 26, 2016

Increased Manhours when Importing from MSP to P6

Forum Topic

When I import a plan from MSP to P6, the work shown in budgeted labour units increases by approximately 1500hrs. I've tried changing the importing settings as well as the calculation settings on the project but it doesn't seem to make any difference....

Sep 27, 2016