Maintaining a Continuous Critical Path While Using a 24-Hour Calendar for Relationship Lag
Forum TopicDefining a 24 Hour Calendar for scheduling relationship lag works well to schedule the seven day weekly curing of material. The critical activity definition, however, may require adjustment. If you are not monitoring activity constraints then define ...