Hand Fill & Compact

Wiki Page

Loose from side of excavation, including compaction (m3/hr)...   Material Ne 100m 100-200mm 200-300mm exc 300m Loose Sand/Soil 0.85 1.02 1.28 1.69 Clay/Heavy Chalk 0.77 0.92 1.16 1.56 Hoging 0.81 0.97 1.20 1.61 Hardcode 0.71 0.84 1.06 1.41

Feb 6, 2009

Traffic Decking

Wiki Page

Installation of temporary traffic decking, consisting of steel beam decking and concrete panels. A typical rate of = 1.6 m2/hr.

Feb 6, 2009

Dewatering

Wiki Page

To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and ...

Feb 6, 2009

Instrumentation

Wiki Page

A typical rate of 3 days per instrument can be used to calculate detailed ground monitoring scenarios.  

Feb 6, 2009

Grouting

Wiki Page

Vertical Grout Curtain Application of grout curtain. A typical rate of 6.20 hrs/m run.

Feb 6, 2009

Rail Grab

Wiki Page

Machine Rail Mounted Hydraulic Grab Rate of 30 - 50 m3 of sand per hour (dependant upon depth), with 1.5 m3 made (2.0 m3 bucket) with each machine lift. Giving a required lift rate of 2.4 mins. A rate of 37 m3/hr (per rig) was achieved on HK Station ...

Feb 6, 2009

Crane Grab

Wiki Page

Tender rates are often quoted as between 20 and 25 m3/hr. With adequate supervision and sufficient loose spoil material supplied to the crane drop area, these rates can easily be increased. Grabs mounted on crawler cranes, rates depend on... Depth of...

Feb 6, 2009

Hydraulic Excavator

Wiki Page

Tractor with backactor, Massey Ferguson or JCB.3 has a 0.3 m3 bucket. Smaller 360 degree excavator has a 0.4 m3 bucket. JCB.6D, Liebherr 400, Hymak 580 or typical 360 degree machine has a 0.5 m3 bucket. 360 degree excavator machine has a 0.6 m3 bucke...

Feb 6, 2009

Material Weights

Wiki Page

Wagon sizes and tonnage capacities vary and should be taken into consideration. Rock = 2.5 T/m3 Concrete = 2.4 T/m3 Landfill / CDG = 1.9 T/m3 Sand = 1.8 T/m3

Feb 6, 2009

Ground Excavation

Wiki Page

Ground Excavation Rates (m3/hr):Ground TypeBucketBulk WorksBasementsTrenchesSmall & DeepSand/Soil0.3m38.78.07.18.4> 0.4m328.515.425.010.0 0.5m350.020.028.613.3Gravel0.3m37.16.96.14.5 0.4m325.914.322.28.7 0.5m340.018.128.611.1Clay/Chalk0.3m37.16.56.14...

Feb 7, 2009

Excavate & Load

Wiki Page

Excavate Spoil Heaps and Load to Transport (m3/hr): Material0.6 m30.8 m31.0 m31.2 m3Sand/Soil20.025.630.335.7Gravel20.425.631.337.0Clay/Chalk18.523.227.833.3Boulder Clay16.921.324.430.3Note:0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity....

Feb 7, 2009

Spoil By Barge

Wiki Page

Removal / Transportation Of Spoil By Barge: The size, getting material to the facility, location and movement restrictions of the barge loading facilities are critical to production. A 2,000 m3 flat bottom barge, could easily be loaded 1.5 times per ...

Feb 7, 2009

Spoil By Conveyor

Wiki Page

Removal / Transportation Of Spoil By Conveyor: The size and location of the conveyor are critical to production and should be sized according to the most critical peaks in excavation. There are the following parameters to select... Max excavation per...

Feb 7, 2009

Elevated Watercourse

Wiki Page

Modification of an existing 6 m high elevated canal. Normal canal is 12 m in width, to allow single passing on bridge/aqueduct structures, a 5.5 m minimum width is required. Normal depth of water is 1.3 m. Some 4 number "V" shaped piers on 1,200 mm b...

Feb 7, 2009

Floating Track Slab

Wiki Page

Pre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints...

Feb 7, 2009

Asphalt Waterproofing

Wiki Page

Asphalt coatings to prepared concrete surfaces, usually undertaken with a 3 man gang. Horizontal Surfaces = 210 m2/wk Vertical Surfaces = 85 m2/wk

Feb 7, 2009

Bituminous Waterproofing

Wiki Page

Brush applied coatings (tretol etc) to prepared concrete surfaces. A two coat application = 5.0 m2/hr A three coat application = 3.5 m2/hr Sheet materials (bituthene etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 4.0 m2/hr Vertical S...

Feb 7, 2009

Polythene Waterproofing

Wiki Page

Polythene Sheeting Sheet materials (DPC/DPM's etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 20.0 m2/hr

Feb 7, 2009

Bentonite Waterproofing

Wiki Page

Sheeting to be installed and covered over immediately in order to prevent drying out, carried out with a gang of at least 3 people. Horizontal Surfaces = 25.0 m2/hr Vertical surfaces = 15.0 m3/hr

Feb 7, 2009

Epoxy Waterproofing

Wiki Page

Epoxy based material (eliminator etc), a 2 part mix. It is sprayed on and large areas can be completed in a short time. Usually carried out in two coats, good ventilation is required. A one coat application = 75 m2/hr A two coat application = 38 m2/h...

Feb 7, 2009